Steve Shows
has been in contact with the LDWF. Below are the e-mails to
date. |
FOR IMMEDIATE RELEASE Mark I note with substantial concern there has been no posting on the I'll be in the area tomorrow and Wednesday. Mark 10-20-09 We last had an email exchange regarding the "plan " almost a month Steve: Mark The last email exchange that we had concerned the availability of "the Steve J. Shows 9-20-09 Steve:
I suspected salvinia to continue to expand when I decided to curtail all herbicide treatments a few weeks ago for many reasons. The drawdown will begin on the 8th of September. Let’s see what effect the drawdown has.
I have meetings set up in the area with several individuals and or entities on Wed and Thurs. More meetings are set for next week. The meetings are important to my understanding of all the particulars. Many of the issues are complex and demand extensive investigating. I anticipate a first draft of the plan to be completed by the 2nd week of September.
The only thing I want to add to the web site this week are a few more question and answers. I will not expose elements of the plan on the site prior to its completion and approval (until they’re approved, they’re not approved). I’m sure that’s not what you wanted to hear, but that’s the way it has to be. I’m not interested in turning my work on the plan into a chat room. Let me finish my work and eventually everyone will understand what I’ve been up to.
Thanks,
Mark
8-18-09
Mark Almost 30 days have passed since it was identified that you would become the "salvinia czar" on Lk. Bistineau. Since that time, discussions have revolved around development of short and long term plans and that primary communications would be channeled through the LWF website...in the meantime, Salvinia has continued to grow at a rapid rate. Is there an established date for completion of these plans? Also, the data on the website is dormant ..there's been no update in several weeks
Steve J. Shows 8-18-09
Steve:
Without
appearing
to
shoot
at
every
idea
that
comes
my
way
(and
there
are
many)
via
emails,
I
will
respectfully
listen
and
consider
the
concept
while
we
seek
the
long
term
approach.
I
will
tell
you
that
the
plan
to
gain
control
of
giant
salvinia,
or
any
aquatic
weed
issue
is
best
resolved
using
a
comprehensive
approach.
Spraying,
by
itself,
is
ineffective
and
an
unreasonable
approach.
Simply
flying
over
the
lake
will
make
my
case
on
this
point.
As
far
as
the
oil
spill
analogy,
I
would
suggest
that
the
concept,
while
sounding
good
to
those
not
familiar
with
all
the
issues,
does
not
work
here
for
more
reasons
than
I
care
to
go
in
to
here.
The
problem
is
much
more
complex
than
most
believe.
Thanks
for
the
comments
and
ideas,
Mark
7-30-09
That is correct. This decision was based on several factors. Mark McElroy 7-23-09 Mark, Thanks for the timely response. We will look forward to the completion of your plan...in the meantime, is it correct that spraying herbicide has been discontinued until the lake is lowered?
Steve J.
Shows
7-23-09
Steve:
Thanks for the
comments. The
work on the web
site is just
starting and
there will be
new information
added each
week. I am
confident that
information as
to what the
department plans
to do to control
giant salvinia
can be conveyed
via this site,
new releases and
public
meetings. I am
in the early
stages of plan
development and
will require a
few more weeks
to at least
prepare a draft
for Secretary
Robert Barham
primarily due to
the fact that I
don’t have all
the information
I need to make
sound decisions,
yet. I will
continue to meet
with individuals
and
groups/organizations
in the area on
weekly basis in
my efforts.
Thank you for
the work you do
to keep those
folks interested
in L. Bistineau
informed
Mark McElroy 7-23-09 Good morning, I am Steve shows and along with 2 associates, try to maintain communication with some 200 very interested Lk, Bistineau advocates concerning the salvinia efforts. We invite you to visit www.lakebistineau.com which contains a substantial history of exchanges between our small group , LWF and our mailing list. James Seales has been our primary contact over the last 3 years. Further, our group organized the original community meeting (over 300 attendees) at Koran Baptist church in August of 2007. Unfortunately, there has been no visible progress related to salvinia eradications since that time. Today, from my vantage point on the lake, the Salvinia has won. I live on the intersection of the 2 largest and most open areas of the lake, Gregg Lake and Catfish pond. Yesterday and this morning 50%(hundreds of acres) of what should be water is salvinia. There has been no spray activity in weeks. Is it LWF intention to not spray preceding the drawdown? If so, LWF credibility could be enhanced by communicating that to the citizenry. And, if true , the spillway should be opened today to allow more time for dewatering! ...the drawdown tends to remove more salvinia by allowing it to exit through the dam than anything else that has been done! I am forwarding a plan initially construed by Randy Person (see below), a lake resident, which I believe you received directly earlier this week. Segmenting the lake, having the ability to drawdown below the 7 foot limitation appear to have merit and should be given appropriate attention...I understand that you are now the person to do that!
I look forward to your response. Finally congratulations on establishment of the link on the LWF webpage..it'a good first step; however, the content is the important ingredient and the content contained today is old news. The focus should be on what's being done, what is planned and what are the milestones.. ..three years of LWF activity have not yielded visble improvement. I look forward to your timely response
Steve J. Shows 7-23-09
Steve,
It is too early to tell for
sure about the effects of
the Galleon application, the
Sepro representatives will
be on the lake later this
week taking a look at the
salvinia. It is promising
that we have not had any
significant rainfall, so the
Galleon should not have
flushed out of the intended
treatment areas, and
hopefully the herbicide
concentrations can be
maintained for the required
60 – 90 day contact time for
maximum effectiveness.
Over 78,000 lbs of weevil
infested giant salvinia has
been stocked in Lake
Bistineau during the past
two weeks, estimates are
that this material held over
1.8 million adult weevils.
Approximately 50 LDWF
personnel from across the
state were involved in
harvesting, transporting,
and stocking the weevil
infested salvinia in this
massive two week long
effort. The weevils were
stocked in a protected area
which has harbored salvinia
for over two years and will
retain water during the
drawdown.
The District 1 spray crews
have been heavily involved
in preparing for and
conducting the Galleon
application and stocking
weevils for the past 3 weeks
so there has not been as
much spray activity as
normal on Bistineau. We do
plan on bringing additional
spray crews to assist in the
near future.
In response to the
discussion during the
meeting with Secretary
Barham, there were several
ideas that were discussed
and some have sufficient
merit to warrant further
investigation. These
include the capability to
further dewater the lake
during a drawdown past the
7’ drawdown capabilities we
currently have and some
discussion by the police
juries concerning thinning
the cypress timber in
certain areas of the lake.
James Seales
District 1 Fisheries
Biologist Manager
6-29-09
James, Please provide an opinion of the Galleon application, at this early date, is there an overall opinion regarding success potential? Is the relocation of weevils still underway and what is the magnitude of the effort? where are they being placed?.. I haven't noticed any activity...weevil placement and/or herbicide spraying in several weeks! In a monthly civic meeting there was discussion concerning a meeting that local officials had with Sec. Barham and some other politicos last week wherein several thoughts (draining of the lake to the maximum extent,, increasing salinity, etc. ). what do you know of these discussion or , in particular , any speciific results that may be coming forth?
Steve J. Shows
6-22-09
Steve,
Please find attached
(CLICK
HERE TO DOWNLOAD ATTACHMENT)
a synopsis of the giant salvinia problem on
Bistineau and LDWF’s efforts thus far and plans for
this year.
As I indicated earlier the Galleon application will
take place tomorrow and we plan on starting large
scale movement of weevil infested salvinia from
Gheens next week. Other than the drawdown, other
activities are still in the planning stage.
We do not actively politic for funding, but will
work with other organizations in their attempts to
secure outside funding.
Hope this information is helpful.
(CLICK
HERE TO DOWNLOAD ATTACHMENT)
James Seales
District 1 Fisheries Biologist Manager
6-10-09
James, I'm looking at Catfish pond and Gregg lake and both have a very large amount of Salvinia floating about...not quite as bad as when you saw it 2-3 weeks ago; but not passable in a normal outboard motor because of clogging the water intake and overheating...WLF has been responsive and for the most part has performed commendably in difficult circumstances ; however, it is NOT ENOUGH! I think just from casual observation that salvinia is winning and we are in a crisis situation with the primary growing season just beginning. Spraying must be intensified! If we can help by addressing the situation with the legislature for additional resources (spray crews, the consolidated spray crew effort as was done last year, etc.) then, we are ready and more than willing to initiate that action. We can and will play those cards with LWF participating or if you feel it not politically correct to actively participate then we will act independently. Please let us know the near term plan for intensification and your position concerning the pursuit of legislative involvement by June 10 so that we can correctly organize our campaign. Thank You
Steve J. Shows
6-1-09
James, Spray crews continue in this general area with primary emphasis on the South end of Catfish pond. It's absolutely horrible in that area. I boated out today and the mouth of Spring branch where the barrier has been installed is very bad. It does appear the barrier is doing some good in keeping the mess from entering Spring Branch. All around Our Place Bar Grill is very bad and the big Memorial Day event will draw even more negative comments from the Lake users because of the event being so close to the water. I understand that the salvinia washing over the spillway is significant.
Steve J. Shows
5-20-09
James, At least 2 spray crews were dispensing herbicide on and around Fairview point on 5/18 and 5/19 and seemed to concentrate on the bank line between the roadway/levee leading out to my house and Camp Joy. This same area may be an excellent candidate for the Galleon application. It was great to see such an expedited response to our sincere appeal. I understand Mother Nature has also been favorable by washing a tremendous amount of Salvinia over the spillway during this "high" water period. We need all the help we can get. Thanks,
Steve J. Shows
5-19-09
James,
Steve J. Shows
5-15-09
Steve,
I plan on sending the crews your way on Monday. Please
let me know what you see. I looked at your area today
and you are correct in that it is really bad right
there, we had a lot of salvinia flush out of the area
around the State Parks and the wind is pushing it north
when it hit the open water areas.
James Seales
District 1 Fisheries Biologist Manager
5-15-09
James,
As I look to the South from Fairview point, I am estimating the
salvinia is solidly covering this area of the lake from the
north bank of Catfish pond to Spring Branch and from the channel
in Greggs lake to the east bank of Catfish pond...or, as another
perspective 50-70% of Catfish pond is covered with Salvinia ...I
have not seen , heard or had any reports of spray activity !
It would seem to me this would be an ideal time to encapsulate
this area with the boom material; for heavy dosing with
herbicide in a dormant corral. When will the contract sprayers
begin and where? What about the mechanical harvesting? I have
read your estimates of 1500 acres of salvinia coverage , at this
time. Candidly, I think that is an understatement. If more
aggressive treatments are not undertaken, we will not be able to
use the lake because of salvinia NOT because of the lake
drawdown potential. This morning is as bad as I've seen from
this vantage point.
Steve J. Shows
5-15-09
Steve, The predominate southerly winds in this area have pushed large mats of giant salvinia into several areas of the lake where it is causing many problems. There is currently approximately 1500 acres of giant salvinia on Bistineau, and much of it is in very noticeable locations and impeding boat traffic and access for shoreline property owners.
LDWF has five spray crews in the District with two crews assigned to Bistineau. We may also pull in additional crews from other areas of the District in the next few weeks to assist on Bistineau as we have done previously. We also are getting some new surfactants on contract in the near future which are supposed to be more efficient and increase the effectiveness of the foliar herbicide applications.
I received notice yesterday that a work order for the private contractor to begin spraying and he will likely begin spraying in the next week or two. This contract is for treatment of 800 acres of giant salvinia on Lake Bistineau which will supplement what our crews spray.
Due to travel restraints no large-scale applications as was conducted last year are planned. We may utilize a few additional crews from other areas of the state, but I will not have all the crews available as was done last year.
Plans are to test a new herbicide, Galleon, in a couple of coves or isolated pockets on the lake, this herbicide requires a long contact time (60 days minimum) with the giant salvinia so it is not well suited for areas where there is a lot of water exchange as the concentrations will become quickly diluted in the water and be ineffective.
We are waiting to see how effective the contractors, the new herbicides, and new surfactants are prior to deciding on any drawdown plans.
Hope this information is helpful.
James Seales
District 1 Fisheries Biologist Manager
5-12-09
James, I am forwarding another email from a concerned lake user.
Steve J. Shows 5-09-09 James, I am forwarding another email that basically echoes what we've been suggesting for months! I beg to know what is going on. What is the spray crew configuration (one time, I recall it was stated that 4 full time crews were assigned to this district and this would be supplemented by contract sprayers. what is the status!) mechanical harvester? other planned events? the massive spraying effort as was done last year bringing in multi crews from around the state ...casual observations made by frustrated residents are identifying the problem magnitude and begging to know what the LWF is doing and/or planning to do...may we please have an answer in a very short period so that the lake users can be informed...It seems worse everyday?
Steve J. Shows
5-05-09
James, Some graphics of increasing salvinia problems...it appears to be returning with a vengeance. This morning around fairview pt. the salvinia coverage is as bad as it's been in quite a while
Steve J. Shows 5-04-09 Steve,
This response was sent in response to another e-mail from Mr. Rodgers but also covers what is in this version.
Mr. Rodgers,
I can’t advise you to spray the lake yourself, and the herbicide you mentioned, Roundup, is not approved for aquatic use. Certified aquatic herbicide applicators may make applications provided they coordinate with our Department their application plans.
We have 2 spray crews assigned to Lake Bistineau, and we are in the process of supplementing their efforts with contract herbicide applicators to make additional foliar herbicide applications. We are also identifying areas to test a new herbicide, Galleon, which is applied to the water and kills the salvinia slowly over a period of time provided herbicide concentrations remain high enough in the treatment areas.
I will pass this information along to our spray crews.
If I can be of further assistance to you please let me know.
James Seales
District 1 Fisheries Biologist Manager
4-28-09
James, Please give us some feed back, thanks.
Steve J. Shows 4-23-09 James, Since I'm somewhat vocal when not seeing a spray crew, it is equally important that I recognize effort when it happens....and, it happened today...I was in boathouse and the crew came by and was performing what I thought was good spray coverage...thanks
Steve J.
Shows
4-1-09
James, Attempting to keep you aware of lake resident sentiment....FYI, I haven't seen any spraying in several months....at least the high water will wash some of it over the spillway !!
Steve J. Shows 3-31-09
Steve,
You are
correct in
that the
drawdown has
been
beneficial
in reducing
James,
Perhaps,
there has
been
communication
in addition
to this
November 10
Steve,
Steve,
Steve, James,
This is a
representative
sample of
concerns
expressed by
lake
Personally,
I have seen
Steve, James,
What is the
current
planning
related to a
partial
refill of
the Steve,
The gates
were opened
on Bistineau
this morning
by DOTD. The
plan is
Steve,
What's
happening
with the
weevil plan
previously
scheduled
for June
'08?
Steve, James,
I know the
gates are
partially
opened...When
may I expect
to
Has DOTD
reopened the
gates? As
I'm sure you
know the
lake is 2
feet
Steve,
James Seales
4-15-08 Hello James,
How many
days were
you able to
spray? I
know
Thursday was
a loss!
We were
spraying
Aquamaster
last week,
this is a
glyphosate
herbicide
Hello James,
Please see
the
forwarded
emails and
please
provide your
Steve J. Shows 4-14-08
Everything
is on go for
the
herbicide
applications
planned for
next
Steve, Hello James,
I was
thinking
about the
potential
for lake
lowering and
Steve, James,
Are you able
to estimate
the number
of crew
boats that
will be |